CS Energy has completed a portfolio of solar projects in Texas. At 32.7 MWdc, the portfolio will generate enough renewable energy to power more than 5,000 homes each year.
The Texas portfolio is comprised of three separate properties: a 14.5 MW project located in Brooks County; a 7.3 MW site in McLennan County; and a 10.9 MW project in Menard County. 500 miles separate the three sites, which were developed simultaneously.
The Brooks County project utilizes Sunfolding racking and the other two sites utilize Array Technologies trackers. CS Energy provided engineering, procurement, and construction (EPC) services for all three sites and managed the project schedules to ensure the portfolio was delivered on time.
“As a national EPC, it’s imperative that our solar projects meet our rigorous standards no matter the conditions. I’m proud that we have met the challenges of this multifaceted project and am pleased to deliver a solar energy portfolio that will make clean energy more accessible for the residents and businesses of Texas.”
Matthew Skidmore, CEO of CS Energy.
The Texas solar projects provide power directly to two separate utilities, with the McLennan and Menard County sites supplying energy to Oncor Electric Delivery and the Brooks County site delivering solar power to AEP Energy.