Close Menu
Energy NewsEnergy News
  • NEWS
    • Breaking News
    • Hydrogen
    • Energy Storage
    • Grid
    • SMR
    • Projects
    • Production
    • Transport
    • Research
  • SPOTLIGHT
    • Interviews
    • Face 2 Face
    • Podcast
    • Webinars
    • Analysis
    • Columnists
    • Reviews
    • Events
  • REGIONAL
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle east
    • Pacific
  • COMMUNITY
  • ABOUT
    • Advisory Board
    • Contact us
    • Report Your News
    • Advertize
    • Subscribe
LinkedIn X (Twitter) YouTube Facebook
Trending
  • South Korea’s Largest Hydrogen-Only Fuel Cell Plant Begins Operation in Ulsan
  • Ingeteam Commissions Castilla y León’s First Green Hydrogen Plant
  • Norway’s Karmsund Hydrogen Project to Begin Operations in 2028
  • ITM Power Bets on ‘Hydrogen-as-a-Service’ with New German Subsidiary Hydropulse
  • Greece Weighs Hydrogen Ambitions Against Power Costs and Lack of Subsidies
  • Teesside to Anchor £96M Pipeline Push as Ofgem Backs East Coast Hydrogen Network
  • RIC Energy Secures Site for 220MW Hydrogen-Based E-Fuels Project in Castilla y León
  • ITM Power Gets FEED Contract for Uniper’s Humber H2ub
LinkedIn X (Twitter) YouTube Facebook
Energy NewsEnergy News
  • NEWS
    • Breaking News
    • Hydrogen
    • Energy Storage
    • Grid
    • SMR
    • Projects
    • Production
    • Transport
    • Research
  • SPOTLIGHT
    • Interviews
    • Face 2 Face
    • Podcast
    • Webinars
    • Analysis
    • Columnists
    • Reviews
    • Events
  • REGIONAL
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle east
    • Pacific
  • COMMUNITY
  • ABOUT
    • Advisory Board
    • Contact us
    • Report Your News
    • Advertize
    • Subscribe
Energy NewsEnergy News
Home Home - Europe
Green Hydrogen H2 News

A quarter of German wind turbines at risk of going offline as fixed remuneration expires

Arnes BiogradlijaBy Arnes Biogradlija24/09/20202 Mins Read
Share
LinkedIn Twitter Facebook Email WhatsApp Telegram

Almost a quarter of Germany’s wind turbines require a new business model when fixed payments under the country’s Renewable Energy Act (EEG) expire after their 20-year guaranteed support period, says a study by digital energy system solutions provider Nefino.

The study commissioned by Swiss energy company Alpiq also found that minimum distance rules for wind parks to the nearest settlement make it difficult to replace old turbines with new larger ones.

“The consequences vary greatly from region to region. Northern federal states, where wind energy was expanded early on, are more affected by the end of EEGsupport than southern Germany.”

Nefino’s Jan-Hendrik Piel.

Fifty-two percent of the 8,700 facilities affected by distance rules and expiring renewables payments are located in the four northern German states Lower Saxony, Brandenburg, Mecklenburg Western Pomerania and Schleswig-Holstein.

However, overall the distance rules have more impact in the south: In Baden-Wuerttemberg, only 16 percent of facilities can be modernised, in Bavaria even less, according to the study.

To keep turbines running at a profit, Alpiq proposes so-called power purchase agreements (PPA), often long-term delivery agreements that many experts think will become the new default procedure after the feed-in tariff period ends.

Starting in 2021 and throughout the 2020s, many of Germany’s pioneer wind turbines, solar PV installations and biogas plants will stop receiving fixed feed-in tariffs, meaning many gigawatts in renewable capacity may be shut down if they can’t find a new business model to run on.

This potential loss of renewable power capacity comes at a decisive time for Germany’s energy transition, as the country plans to increase the share of renewables in power consumption in order to reach its emission reduction targets and to gradually increase the use of electricity in all sectors.

Share. LinkedIn Twitter Facebook Email

Related Posts

Hydrogen

South Korea’s Largest Hydrogen-Only Fuel Cell Plant Begins Operation in Ulsan

25/06/2025
Hydrogen

Ingeteam Commissions Castilla y León’s First Green Hydrogen Plant

25/06/2025
hydrogen

Norway’s Karmsund Hydrogen Project to Begin Operations in 2028

25/06/2025
hydrogen

ITM Power Bets on ‘Hydrogen-as-a-Service’ with New German Subsidiary Hydropulse

25/06/2025
hydrogen

Greece Weighs Hydrogen Ambitions Against Power Costs and Lack of Subsidies

25/06/2025
hydrogen

Teesside to Anchor £96M Pipeline Push as Ofgem Backs East Coast Hydrogen Network

24/06/2025
Hydrogen

South Korea’s Largest Hydrogen-Only Fuel Cell Plant Begins Operation in Ulsan

25/06/2025
Hydrogen

Ingeteam Commissions Castilla y León’s First Green Hydrogen Plant

25/06/2025
hydrogen

Norway’s Karmsund Hydrogen Project to Begin Operations in 2028

25/06/2025
hydrogen

ITM Power Bets on ‘Hydrogen-as-a-Service’ with New German Subsidiary Hydropulse

25/06/2025

Subscribe to Updates

Get the latest news from the hydrogen market subscribe to our newsletter.

LinkedIn X (Twitter) Facebook YouTube

News

  • Inteviews
  • Webinars
  • Hydrogen
  • Spotlight
  • Regional

Company

  • Advertising
  • Media Kits
  • Contact Info
  • GDPR Policy

Subscriptions

  • Subscribe
  • Newsletters
  • Sponsored News

Subscribe to Updates

Get the latest news from EnergyNewsBiz about hydrogen.

© 2025 EnergyNews.biz
  • Privacy Policy
  • Terms
  • Accessibility

Type above and press Enter to search. Press Esc to cancel.