Arnes Biogradlija is the founder and Editor in Chief of EnergyNews.biz, which he launched in 2021 to separate energy transition realities from fairy tales. He writes data driven analysis on hydrogen, energy storage, small modular reactors, grids and industrial policy, and leads the Energy Talks interview series. EnergyNews.biz reporting has been cited more than 100 times by the International Energy Agency.

Widely quoted estimates put the capital cost of 100 MW of data center capacity at $900 million to more than $1.8 billion depending on facility type, and they do not necessarily include servers and GPUs. Epoch AI’s May 2026 model implies the building is about 30% of the upfront capital for a GB200 NVL72 campus, while Cushman & Wakefield finds costs up 21% per MW in under two years. The ranges are plausible, but they describe one layer of the cost stack. Epoch AI’s May 2026 model of a typical US hyperscaler AI campus puts upfront capital at $37.9 billion…