Close Menu
Energy NewsEnergy News
  • NEWS
    • Breaking News
    • Hydrogen
    • Energy Storage
    • Grid
    • SMR
    • Projects
    • Production
    • Transport
    • Research
  • SPOTLIGHT
    • Interviews
    • Face 2 Face
    • Podcast
    • Webinars
    • Analysis
    • Columnists
    • Reviews
    • Events
  • REGIONAL
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle east
    • Pacific
  • COMMUNITY
  • ABOUT
    • Advisory Board
    • Contact us
    • Report Your News
    • Advertize
    • Subscribe
LinkedIn X (Twitter) YouTube Facebook
Trending
  • EU–China Energy Diplomacy Amid German Hydrogen Retrenchment: A Deep Dive
  • Merredin BESS Secures $220M Financing but Pays Premium over Global Battery Cost Benchmarks
  • Brazil Stakes Claim in Global Hydrogen Race with €1.3B Investment in Uberaba and Açu Projects
  • Bremen Project Collapse Reveals Fragile Economics Behind Germany’s Green Hydrogen Hopes
  • The Hydrogen Heating Mirage: Why Germany’s “H₂-Ready” Promise Risks Locking in High Costs and Low Returns
  • How Lyten’s Salvage Mission Could Upend Europe’s Battery Wars
  • Doug Wicks on Why Energy Innovation Is Broken—and How to Fix It
  • Cost and Policy Roadblocks Stall LEAG’s H2UB Boxberg Green Hydrogen Hub
LinkedIn X (Twitter) YouTube Facebook
Energy NewsEnergy News
  • NEWS
    • Breaking News
    • Hydrogen
    • Energy Storage
    • Grid
    • SMR
    • Projects
    • Production
    • Transport
    • Research
  • SPOTLIGHT
    • Interviews
    • Face 2 Face
    • Podcast
    • Webinars
    • Analysis
    • Columnists
    • Reviews
    • Events
  • REGIONAL
    • Africa
    • Americas
    • Asia
    • Europe
    • Middle east
    • Pacific
  • COMMUNITY
  • ABOUT
    • Advisory Board
    • Contact us
    • Report Your News
    • Advertize
    • Subscribe
Energy NewsEnergy News
Home Home - Europe
Green Hydrogen H2 News

Final turbines installed at SeaMade

Arnes BiogradlijaBy Arnes Biogradlija01/12/20202 Mins Read
Share
LinkedIn Twitter Facebook Email WhatsApp Telegram

Construction works at SeaMade, Belgium’s largest offshore wind farm, have crossed the finish line with the last of 58 turbines successfully installed.

The SeaMade wind farm will provide green energy for 485,000 households and will lead to a significant reduction of annual CO2 emissions of at least 500,000 tonnes.

The offshore construction of the SeaMade wind farm began in September 2019 with the installation of the foundations. DEME was responsible for the Engineering, Procurement, Construction and Installation (EPCI) of the foundations, turbines, inter-array and export cables, as well as for the installation of two offshore substations. DEME’s DP2 offshore installation vessel ‘Apollo’ installed 58 Siemens Gamesa 8.4 MW turbines on the monopile foundation.

“Completing this large-scale project in such a short timeframe could only be achieved because of the integrated Balance of Plant approach and through extensive cooperation with our client, as well as the relentless efforts and determination of all the teams involved. This was also the first turbine installation project for ‘Apollo’. The crew has put in an excellent performance, particularly given the extra coronavirus restrictions they faced. At DEME we are all very proud to have played a key role in the development of this important wind farm, which is a vital step in helping to realise the Belgian government’s ambitious climate targets.”

Bart De Poorter, general manager DEME Offshore.

“Claiming that 2020 has been an eventful year for Otary is quite an understatement. However with the SeaMade project, Otary has now realised the largest offshore wind farm in the Belgian North Sea on time and on budget despite these challenging times. All parties were well determined to deliver the project before year-end 2020, as instigated by the Belgian government. Mission accomplished. Through many contributions of contractors and team members, even COVID-19 could not stop or delay our project, which remains quite remarkable! Sincere thanks to the whole Otary team and all parties involved for achieving this impressive milestone. This is only possible through an incredible commitment, dedication and a countless number of hours of all the project teams.”

Mathias Verkest, CEO SeaMade and Otary.
Share. LinkedIn Twitter Facebook Email

Related Posts

Hydrogen

EU–China Energy Diplomacy Amid German Hydrogen Retrenchment: A Deep Dive

02/07/2025
BESS

Merredin BESS Secures $220M Financing but Pays Premium over Global Battery Cost Benchmarks

02/07/2025
hydrogen

Brazil Stakes Claim in Global Hydrogen Race with €1.3B Investment in Uberaba and Açu Projects

02/07/2025
Hydrogen

Bremen Project Collapse Reveals Fragile Economics Behind Germany’s Green Hydrogen Hopes

02/07/2025
Hydrogen

The Hydrogen Heating Mirage: Why Germany’s “H₂-Ready” Promise Risks Locking in High Costs and Low Returns

02/07/2025
Battery

How Lyten’s Salvage Mission Could Upend Europe’s Battery Wars

02/07/2025
Hydrogen

EU–China Energy Diplomacy Amid German Hydrogen Retrenchment: A Deep Dive

02/07/2025
BESS

Merredin BESS Secures $220M Financing but Pays Premium over Global Battery Cost Benchmarks

02/07/2025
hydrogen

Brazil Stakes Claim in Global Hydrogen Race with €1.3B Investment in Uberaba and Açu Projects

02/07/2025
Hydrogen

Bremen Project Collapse Reveals Fragile Economics Behind Germany’s Green Hydrogen Hopes

02/07/2025

Subscribe to Updates

Get the latest news from the hydrogen market subscribe to our newsletter.

LinkedIn X (Twitter) Facebook YouTube

News

  • Inteviews
  • Webinars
  • Hydrogen
  • Spotlight
  • Regional

Company

  • Advertising
  • Media Kits
  • Contact Info
  • GDPR Policy

Subscriptions

  • Subscribe
  • Newsletters
  • Sponsored News

Subscribe to Updates

Get the latest news from EnergyNewsBiz about hydrogen.

© 2025 EnergyNews.biz
  • Privacy Policy
  • Terms
  • Accessibility

Type above and press Enter to search. Press Esc to cancel.