The Poland AP1000 project is lining up its next equipment orders. State company Polskie Elektrownie Jądrowe (PEJ) has signed a letter of intent with the Westinghouse-Bechtel consortium to extend the Engineering Development Agreement to cover procurement of long-lead items for the first unit of Poland’s first nuclear power plant. The letter was signed during the 7th Ministerial Meeting of the Partnership for Transatlantic Energy Cooperation in Warsaw.

Three Westinghouse AP1000 reactors are planned at the Lubiatowo-Kopalino site in Choczewo, Pomerania, in northern Poland. The design uses modular construction, with dozens of steel and concrete structural and mechanical modules built in factories and installed on site.

Poland AP1000 orders so far

In October, PEJ gave Westinghouse the go-ahead to order long-lead items for the first unit, covering six key components of the nuclear island including the containment vessel and associated structural modules. Westinghouse then placed conditional purchase orders with four Polish firms: the CA02 walls module scope with Mostostal Kielce, the CA03 module scope with Energomontaż-Północ Gdynia, the CA05 walls module scope with Mostostal Kraków and the CA20 floors module scope with FAMAK. Earlier this month, Japan’s IHI Corporation received an order covering engineering and procurement for one containment vessel and an associated large steel module.

An ENB calculation puts the plant in context. At roughly 1,250 MWe gross per AP1000 unit, three units add up to about 3.75 GW, a large share of Poland’s future firm low-carbon capacity in a power system still dominated by coal.

Poland AP1000 chart: planned capacity of the three-unit plant
Approximate gross capacity of the planned Lubiatowo-Kopalino plant. ENB calculation based on about 1,250 MWe per AP1000 unit.

Why early long-lead orders matter

Long-lead items such as reactor vessels, steam generators and containment components take years to manufacture. Ordering them early is one of the few levers a project owner has to protect a schedule. PEJ said that starting procurement for the next batch early will help reduce scheduling risk and ensure the plant is commissioned on time.

Under the new letter, PEJ and the consortium will also work on a mechanism to extend contract scopes that are critical to the schedule. The US partners will support PEJ in talks with export credit agencies on financing for the supply of plant components.

Energy Minister Miłosz Motyka said the plant is a strategic project that will strengthen energy security for decades, and that Polish companies are playing an increasingly important role. For local suppliers, the module packages already awarded are a reference that can open doors to later units and to other AP1000 projects in Europe.

What Poland AP1000 work means for suppliers

Modular construction shifts value from the site to the factory. Each structural module is a large welded steel assembly that is later filled with concrete on site, so firms with heavy fabrication capacity, coded welding procedures and nuclear quality assurance stand to win repeat work. The Poland AP1000 orders give four domestic companies that experience, which can be reused for the second and third units.

The conditional nature of the orders is worth noting. They depend on later investment decisions and financing, so suppliers carry some risk if the schedule slips. Even so, early involvement gives them a head start on qualification, which is often the slowest step for a new nuclear supplier.

Poland AP1000 and the wider build

Poland joins a growing list of countries moving from plans to procurement, part of a global build that is at its highest in more than 35 years, as set out in the analysis of nuclear construction. Smaller designs are also advancing in the region, though most remain at an earlier stage, as the review of the small modular reactor wave noted.

The next milestones for the Poland AP1000 programme are the follow-on long-lead contracts, the financing package with export credit agencies and the construction licence. Updates are published by Polskie Elektrownie Jądrowe.