Grid expansion is the part of the energy transition that rarely makes headlines, and the International Energy Agency’s World Energy Outlook 2026 puts a number on it that is hard to ignore. Over the next decade, the world needs about 25 million km of new power lines and about 15 million km of upgraded lines to keep pace with demand and new generation.
The global grid today is roughly 80 million km long, the result of more than a century of building. The outlook asks for an addition equal to close to a third of that in ten years, plus upgrades to a further large share of the existing network.
Grid expansion in daily terms
The figures become clearer when broken down. Twenty-five million km over ten years is 2.5 million km a year. Divided by 365 days, that is about 6,800 km of new line every day, longer than the distance from Lisbon to Moscow, built every day for a decade. Adding the 15 million km of upgrades brings the total grid work to about 4 million km a year.
Another comparison: 2.5 million km a year is about 62 times the circumference of the Earth at the equator. Most of that length is distribution lines in cities and towns, not long-distance transmission, but both are needed. Distribution networks carry the load from heat pumps, chargers and rooftop solar, while transmission brings large volumes of renewable power from remote sites to demand centres.

Where the money is going
Spending is rising, though not yet everywhere at the needed rate. In the United States, grid investment grew from about $73 billion in 2020 to about $118 billion in 2025, an increase of about 62% in five years. The IEA expects it to settle at around $140 billion a year after that, a further rise of about 19% on the 2025 level.
The money flows mainly to distribution and to replacing ageing equipment, while new interregional transmission remains slow to plan and permit. That pattern is common across advanced economies, and it is why the agency treats grid expansion as a bottleneck rather than a background task. Emerging economies face a different problem: access to affordable capital for projects with long payback periods. For them, grid expansion competes with every other public investment, and the cost of borrowing can double the lifetime cost of a line.
The supply chain behind grid expansion
Cables, transformers and high-voltage converters are the physical limits. Lead times for large power transformers have stretched to several years, and makers of high-voltage direct current equipment have order books filled well into the next decade. Countries are responding with standardisation, as in the framework agreement to build a standard HVDC platform in Turkiye, which lets utilities order repeatable designs instead of bespoke ones.
Operators are also trying to squeeze more out of the existing network before new lines arrive. Dynamic line rating, advanced conductors and grid-enhancing technologies can raise the capacity of a corridor without rebuilding it. Market design matters too: price signals such as Germany’s imbalance prices reward flexibility that eases congestion.
The measure that matters
For grid expansion, the number to follow is kilometres of transmission and distribution line commissioned each year, compared with the 2.5 million km annual requirement. Few countries publish that figure consistently, which is part of the problem: what is not measured is rarely managed. Without a matching build rate, the generation and electrification goals elsewhere in the outlook cannot be met, because power that cannot be delivered is power that is curtailed. The full grid analysis is published in the IEA World Energy Outlook 2026.